The vigilance department observed that the officers who were involved in planning and execution of the project violated the rules and regulations, Central Public Works Department manuals, and Central Vigilance Commission guidelines, and committed various lapses and irregularities while constructing a new building in the guidance of addition and alteration of the CM residence.”…directed to explain as to why disciplinary action should not be initiated as per relevant rules, laws, manuals, circulars, CVC guidelines etc for the mentioned lapses and irregularities,” the showcause notices read , seeking reply in 15 days.
The engineers who were served notices through the principal secretary of PWD included principal chief engineer AK Ahuja, chief engineers Ashok Kumar Rajdev and PK Parmar, superintending engineer Abhishek Raj, executive engineers Vinay Chaudhary and Shibnath Dhara, and assistant engineer Rajat Kant.
While Raj and Parmar said they were not aware of the notices, the other engineers could not be reached for their reactions.